Skip To Main Content

Waterslide Project & FAQs

November 2026 Update

The wait is over! The Snohomish Aquatic Center waterslide has officially reopened, and we couldn't be more excited to welcome everyone back for some sliding fun.

This project has been a long journey, and we are incredibly grateful to our community for patience, understanding and continued support. We also want to say thank you for the flexibility as we worked through the challenges along the way to bring this exciting feature back to the facility.

We know how much the waterslide means to our guests and community, and we're thrilled to see it back in action.

 

Find it Fast

If you have any questions, please contact us at swim@snohomishaquatic.com 
or call 360-568-8030 to speak with a Guest Services representative. 

February 2026 Waterslide Update

In late 2023, a significant structural issue was identified in the concrete base supporting the waterslide. The district has worked closely with structural engineers, contractors, and aquatic facility experts to fully understand the issue and develop a long-term solution. This work confirmed that the repairs are extensive and would require full removal and replacement of the concrete stairway, slide tower, and a portion of the facility’s exterior glass wall. The actual slide does not need to be replaced.  

We are moving forward with the next phase of this important project. Work on the waterslide base will begin in April and will take place in two phases: demolition and construction of the new slide tower. Guests should expect to see workers, scaffolding, materials, and equipment onsite throughout the duration of the project.  

During each phase, we will need to temporarily close the Recreation Pool area for a period in the mornings and afternoons on weekdays. Additional temporary closures are possible as work progresses.    

We understand how important the Recreation Pool is to our guests and the role it plays in daily routines and throughout this process, we are making every effort to minimize disruption and reduce the impact on our community’s programs held in the Recreation Pool, while ensuring the work is completed safely and efficiently.  

Update: September 2026

Phase 2: Tower construction and stair installation 

Crews will return to the Snohomish Aquatic Center beginning the week of October 5 to continue Phase 2 of the waterslide project. This phase includes construction of the new stair tower, and installation of the stairs.

Guests could experience some construction noise while this work is underway.

At this time, we do not anticipate a Recreation Pool closure like the one required during Phase 1. The Recreation Pool and its amenities are expected to remain available to guests throughout Phase 2, although construction activity may cause occasional noise and other temporary inconveniences.

Once the stair and tower work is complete, additional plumbing and electrical work will be needed before the waterslide can return to service. We do not have a reopening date for the waterslide at this time, but we will continue to keep our guests informed as the project progresses and we have more information to share.

We know how much our community values the waterslide and Recreation Pool amenities, and we appreciate your patience and flexibility as this important work continues. We’re looking forward to celebrating the return of the waterslide with our guests!


Phase 1: Demolition (Mid-April through Mid-June) 

Beginning in mid-April and continuing through approximately mid-June, demolition work will take place in the Recreation Pool area. During this time, construction crews and materials will be onsite. As a result, the inflatable slide will not be available, as that space will be used for construction activities. Please note that the planned closure dates are subject to change if needed. 

The two-week closure is behind us, but demolition crew is still on site through mid-June. Guests should expect intermittent noise during this time.

Two-week weekday closure of the Recreation Pool 


Please note:
  • The Recreation Pool will be closed to all activities during this time.
  • Afternoon and evening swim lessons will be held as scheduled.
  • The Recreation Pool will reopen at 3:30 p.m. on Monday.

  • To safely complete demolition work, the Recreation Pool will be closed on weekdays from 5 a.m.–5 p.m., Monday through Friday (April 27-May 8). Dates are subject to change. 
  • Weekends will not be impacted. 

  • The Competition Pool will remain open as usual. 

Please see FAQs below for more information.

This temporary weekday closure will affect morning and afternoon Recreation Pool programs and activities, including: 
  • Water fitness 
  • Open fitness 
  • Hot tub access 
  • Preschool Beach 
  • Private swim lessons 
  • Homeschool lessons 
  • Swim lessons (Spring Session 2) 
Homeschool and group swim lessons (Spring Session 2)
  • Due to the weekday closure (April 27-May 8), Spring Session 2 morning and afternoon swim lessons scheduled before 5 p.m. will be reduced from five weeks to three weeks. Saturday lessons will continue with the normal five-week schedule. 
  • Impacted lessons will be prorated accordingly. 
  • We strongly encourage families to register for Spring Session 2 as planned. These lesson spots remain valuable for continued skill development and help secure priority registration for Spring Session 3. 
Private swim lessons 
  • During the weekday closure (April 27-May 8), all private lessons scheduled before 5 p.m. will be paused. Lessons will resume on Monday, May 11. 
  • Saturday and Sunday private lessons will continue as scheduled and will not be affected. 

Two-week closure FAQs